Campus Improvements and Construction Updates

Construction of the Liebman Science Center

Select Menu from top, left corner of image for additional viewing options

Fire Truck Storage Building

With the gift of a retired fire truck to the Fire Science Dept. a place to store this truck is needed. The college will make room for this new truck by refurbishing space in and around the 2 storage buildings near the D building. This work will begin in late May and be completed in late June.

Work is complete.

Updated: Tuesday, August 01, 2017

Building E Entry and Exit

The second floor entrance at the north end of Building E will be closed starting the week of July 31 for the duration of the Liebman Science Center construction project. To enter Building E from Parking Lot E use the temporary sidewalk leading from Parking Lot E to the first floor entrance behind the Black Box Theater.  This will be the main entrance and exit to the east and north sides of Building E for the duration of the construction project. This access is not ADA accessible. For an ADA accessible entrance into Building E please park in Parking Lot C and enter Building E through the lower level doors.

Updated: Thursday, July 27, 2017

Liebman Science Building Construction Project

Physical work has begun on the new Liebman Science Building at McHenry County College. Excavation has begun on the building itself with concrete starting late the week of July 31.

Demolition of the north entrance into Building E will start the week of July 31. This entry point into Building E will be closed for the duration of the construction project.

Updated: Thursday, July 27, 2017

Way Finding Signage

The Way-Finding signage will continue with installations happening Friday, July 28 and Wednesday-Thursday, August 2-3. 

Updated: Thursday, July 27, 2017