Campus Improvements and Construction Updates

Entrance into Room A124

There will be a new entry door installed at A124. The new entry will allow access from the main hallway instead of off the side hallway. This work is scheduled to begin Wednesday 5/25 and continue through the week of June 6.

Updated: Monday, April 11, 2016

Seal Coat Parking Lot F

Parking Lot F will be seal coated and restriped this spring. Currently this work is scheduled for the week of May 23, specific dates will be scheduled around the weather. The work will take between 2-3 days. If the weather does not cooperate we will reschedule accordingly. Updates will follow.

 During this work the parking lot will be closed.

Updated: Monday, April 11, 2016

Locker Room Update 3

The tile floors and shower walls in the women's and men's locker rooms will be updated with epoxy and Sani-glaze installations during the weeks of 5/23 and 5/30. These processes will update the existing flooring and wall tile, provide a cleaner look and extend the life of the existing products. During this work the locker rooms will be closed.

Updated: Monday, April 11, 2016

Building A Roof Project

Building A will be undergoing a roof replacement beginning the week of May 16, 2016.

The project is expected to take 8-10 weeks (weather permitting). An area of the B parking lot outside the multi-purpose room and the Pod entry will be roped off to allow for construction activities to take place in a controlled environment. Parking in the B lot will be available away from this roped off area. Please use caution when walking through this parking area during daily construction activities. During this time there may be some increased noise and temporary reassignments of classes to minimize disruption.

Updated: Tuesday, March 01, 2016

Locker Room Update 1

The lockers and bathroom partitions in the women's and men's locker rooms will be painted during the week of 5/16. This work will highlight the college's colors and help promote the MCC brand. During this time the locker rooms will be closed.

Updated: Tuesday, March 01, 2016

Multi-Purpose Room Floor

The annual maintenance on the hardwood flooring in the multi-purpose room will be performed on Tuesday 5/17. This work will require the multi-purpose room to be closed for use for the remainder of the week, through Sunday 5/22.

Updated: Tuesday, March 01, 2016

Electrical Grounding Work

An extensive investigation after the lightning strike damage from July of 2015 revealed a lack of full grounding in several of the main switchgear components here at the college. These deficiencies will be addressed during the weeks of 5/16 and 5/23 by a local electrical contractor. Electrical interruptions to the facility will be minimal and work should not interrupt daily activities.

Updated: Tuesday, March 01, 2016