Campus Improvements and Construction Updates

Gyn Floor Screen/Coat

Annual maintenance on the gym floor will be done the week of May 22.

Updated: Tuesday, May 09, 2017

Refresh Cafe Bathrooms

The women's and men's washrooms adjacent to the Café will be refreshed beginning the week of May 15. Work will continue for approximately 3 weeks to get the refresh completed. Men's and Women's washrooms will be available for use down the hallway in the A building and the opposite direction in the C building.

Updated: Tuesday, May 09, 2017

Monument Signs

Construction has started on the 4 new monument signs here at the College. Work will continue into late August before all four of the signs are complete.

Project is complete

Updated: Tuesday, May 09, 2017

Parking Lot A Construction

Parking lot A has the gravel base in place. Look for the first lift of asphalt to be installed by August 9 with the final lift coming shortly thereafter.

project is complete

Updated: Tuesday, May 09, 2017

Building D RTU's

The first 5 of the RTU units have been set and are operating. The final unit was placed on the roof on August 2 and should be fully operational by August 10.

Project is complete

Updated: Tuesday, May 09, 2017

Building A Roof Project

The roofing project on Building A is coming to a close. Tear off and replacement will be complete by August 11 with trim activities continuing for another week to ten days for final completion.

Complete

Updated: Tuesday, May 09, 2017

Seal Coat Parking Lots B and D

Parking lots B and D will be seal coated in late May pending dry weather.

Updated: Tuesday, May 09, 2017

Fire Truck Storage Building

With the gift of a retired fire truck to the Fire Science Dept. a place to store this truck is needed. The college will make room for this new truck by refurbishing space in and around the 2 storage buildings near the D building. This work will begin in late May and be completed in late June.

Updated: Tuesday, May 09, 2017

HVAC System Replacement Building E

The two roof top HVAC units on Building E will be replaced beginning the week of May 15. Look for a crane truck to be on-site for only one day to lift off the old units and install the new units. Once these are in place all work will be confined to space around the specific units. Work should be completed by May 29.

Updated: Tuesday, May 09, 2017

Way Finding Signage

New way finding signs will be installed across campus as part of the campus signage rebranding campaign started two years ago. The work begins the week of May 8 and will continue through the end of May.

Updated: Tuesday, May 09, 2017