Campus Improvements and Construction Updates

Monument Signs

Construction has started on the 4 new monument signs here at the College. Work will continue into late August before all four of the signs are complete.

Updated: Thursday, August 04, 2016

Parking Lot A Construction

Parking lot A has the gravel base in place. Look for the first lift of asphalt to be installed by August 9 with the final lift coming shortly thereafter.

Updated: Thursday, August 04, 2016

Building D RTU's

The first 5 of the RTU units have been set and are operating. The final unit was placed on the roof on August 2 and should be fully operational by August 10.

Updated: Thursday, August 04, 2016

Building A Roof Project

The roofing project on Building A is coming to a close. Tear off and replacement will be complete by August 11 with trim activities continuing for another week to ten days for final completion.

UNDERWAY

Updated: Thursday, August 04, 2016

Locker Room Update 3

The tile floors and shower walls in the women's and men's locker rooms will be updated with epoxy and Sani-glaze installations during the weeks of 5/23 and 5/30. These processes will update the existing flooring and wall tile, provide a cleaner look and extend the life of the existing products. During this work the locker rooms will be closed. 

COMPLETE

Updated: Wednesday, June 22, 2016

Entrance into Room A124

There will be a new entry door installed at A124. The new entry will allow access from the main hallway instead of off the side hallway. This work is scheduled to begin Wednesday 5/25 and continue through the week of June 6.

COMPLETE

Updated: Wednesday, June 22, 2016

Electrical Grounding Work

An extensive investigation after the lightning strike damage from July of 2015 revealed a lack of full grounding in several of the main switchgear components here at the college. These deficiencies will be addressed during the weeks of 5/16 and 5/23 by a local electrical contractor. Electrical interruptions to the facility will be minimal and work should not interrupt daily activities.

COMPLETE

Updated: Wednesday, June 22, 2016

Multi-Purpose Room Floor

The annual maintenance on the hardwood flooring in the multi-purpose room will be performed on Tuesday 5/17. This work will require the multi-purpose room to be closed for use for the remainder of the week, through Sunday 5/22.

WORK COMPLETE 5/18/16

Updated: Tuesday, May 24, 2016

Locker Room Update 1

The lockers and bathroom partitions in the women's and men's locker rooms will be painted during the week of 5/16. This work will highlight the college's colors and help promote the MCC brand. During this time the locker rooms will be closed.

WORK COMPLETED 5/18/16

Updated: Tuesday, May 24, 2016

Seal Coat Parking Lot F

Parking Lot F will be seal coated and restriped this spring. Currently this work is scheduled for the week of May 23, specific dates will be scheduled around the weather. The work will take between 2-3 days. If the weather does not cooperate we will reschedule accordingly. Updates will follow.

 During this work the parking lot will be closed.

PROJECT IS COMPLETE

Updated: Tuesday, May 24, 2016